Vetting and screening of candidates took up to four times longer than G4S expected, contributing to its failure to deliver on its £238m London Olympic and Paralympic Games contract.
Fri, 28 Sep 2012
Vetting and screening of candidates took up to four times longer than G4S expected, contributing to its failure to deliver on its £238m London Olympic and Paralympic Games contract.
This is one of the findings of a review by consultants PwC into G4S’s failure to fulfil its contract with Games organisers LOCOG to supply 10,400 security personnel to...