PAC report slams MoD project management_2
17 August 2012
A £3 billion overrun on the Ministry of Defence’s 25 largest procurement projects has been described as “unacceptable” and management of its major projects as “weak in almost every aspect”, in a repor
A £3 billion overrun on the Ministry of Defence’s 25 largest procurement projects has been described as “unacceptable” and management of its major projects as “weak in almost every aspect”, in a report by the House of Commons’ Public Accounts Committee.
Commenting on the Major Projects Report for 1997, committee chair David Davies also criticised the effectiveness...