Purchasing practices for construction of the Jubilee Line Extension were incompetent, says consulting engineer Ove Arup.


Purchasing practices for construction of the Jubilee Line Extension were incompetent, says consulting engineer Ove Arup. London Underground and the Jubilee Line Extension Project team released incomplete purchasing packages to technical services contractors at tender stage, resulting in change and delays, said Ove Arup. Works contractors were procured individually...